May 12, 2026
CONSTRUCTION UPDATE:
SOUTH OF UNION STREET: The final layer of asphalt paving will continue this week on South 2nd Street on Thursday, May 13 extending from LONG Street to UNION Street. Access will be limited in this section during construction.
NORTH OF UNION STREET: Installation of new water main will continue extending to POPLAR Street. On Wednesday, May 13 installation of curbing and driveway access will begin from UNION Street to ROCK Street.
2nd Street will be CLOSED TO THROUGH TRAFFIC while these sections are under construction. Local traffic will retain access to homes and businesses. Please use caution when driving through the construction zones. Businesses will remain open during construction. For any questions or concerns please call Dennis Overman at 479-857-1189. Thank you for your cooperation and patience.
ACTUALIZACIÓN DE CONSTRUCCIÓN:
AL SUR DE UNION STREET: La capa final de pavimento asfáltico continuará esta semana en South 2nd Street el jueves 13 de mayo, extendiéndose desde LONG Street hasta UNION Street. El acceso estará limitado en esta sección durante la construcción.
AL NORTE DE UNION STREET: La instalación de la nueva tubería principal de agua continuará extendiéndose hasta POPLAR Street. El miércoles 13 de mayo comenzará la instalación de bordillos y accesos a entradas vehiculares desde UNION Street hasta ROCK Street.
2nd Street estará CERRADA AL TRÁFICO DE PASO mientras estas secciones estén en construcción. El tráfico local mantendrá acceso a viviendas y negocios. Por favor, tenga precaución al conducir por las zonas de construcción. Los negocios permanecerán abiertos durante la construcción. Para cualquier pregunta o inquietud, por favor llame a Dennis Overman al 479-857-1189. Gracias por su cooperación y paciencia.
SOUTH OF UNION STREET: The final layer of asphalt paving will continue this week on South 2nd Street on Thursday, May 13 extending from LONG Street to UNION Street. Access will be limited in this section during construction.
NORTH OF UNION STREET: Installation of new water main will continue extending to POPLAR Street. On Wednesday, May 13 installation of curbing and driveway access will begin from UNION Street to ROCK Street.
2nd Street will be CLOSED TO THROUGH TRAFFIC while these sections are under construction. Local traffic will retain access to homes and businesses. Please use caution when driving through the construction zones. Businesses will remain open during construction. For any questions or concerns please call Dennis Overman at 479-857-1189. Thank you for your cooperation and patience.
ACTUALIZACIÓN DE CONSTRUCCIÓN:
AL SUR DE UNION STREET: La capa final de pavimento asfáltico continuará esta semana en South 2nd Street el jueves 13 de mayo, extendiéndose desde LONG Street hasta UNION Street. El acceso estará limitado en esta sección durante la construcción.
AL NORTE DE UNION STREET: La instalación de la nueva tubería principal de agua continuará extendiéndose hasta POPLAR Street. El miércoles 13 de mayo comenzará la instalación de bordillos y accesos a entradas vehiculares desde UNION Street hasta ROCK Street.
2nd Street estará CERRADA AL TRÁFICO DE PASO mientras estas secciones estén en construcción. El tráfico local mantendrá acceso a viviendas y negocios. Por favor, tenga precaución al conducir por las zonas de construcción. Los negocios permanecerán abiertos durante la construcción. Para cualquier pregunta o inquietud, por favor llame a Dennis Overman al 479-857-1189. Gracias por su cooperación y paciencia.